FAQ - About - Contact Us - Tell A FriendFree-Ed.Net Home   Bookmark and Share

WALL FRAMING

LEARNING OBJECTIVE:

Upon completing this section, you should be able to identify wall framing members and explain layout and installation procedures for these members in building construction.

Wall construction begins after the subfloor has been nailed in place, The wall system of a wood-framed buildlng consists of exterior (outside) and interior (inside) walls. The typical exterior wall has door and window openings, as shown in figure 1-33. Interior walls, usually referred to as "partitions," divide the inside area into separate rooms. Some interior walls have door openings or archways.

fig0833.jpg (72057 bytes)

Figure 1-33.—Typical exterior wall.

Partitions are either bearing or nonbearing. Bearing partitions support the ends of the floor joists or ceiling joists. Nonbearing partitions run in the same direction as the joists and therefore carry little weight from the floor or ceiling above.

Traditionally, 2-by 4-inch structural lumber is used for the framed walls of one-story buildings, although the use of heavier structural lumber is specified at certain locations for particular projects. Multistory buildings, for example, require heavier structural lumber. This requirement is specific to the lower levels in order to support the weight of the floors above.

STRUCTURAL PARTS

A wood-framed wall consists of structural parts referred to as "wall components" or "framing members." The components (shown in fig. 1-33) typically include studs, plates, headers, trimmers, cripples, sills, corner posts, and diagonal braces. Each component is essential to the integrity of the total wall structure.

Studs

Studs are upright (vertical) framing members running between the top and bottom plates. Studs are usually spaced 16 inches OC, but job specifications sometimes call for 12-inch and 24-inch OC stud spacing.

Plates

The plate at the bottom of a wall is the soleplate, or bottom plate. The plate at the top of the wall is the top plate. A double top plate is normally used. It strengthens the upper section of the wall and helps carry the weight of the joists and roof rafters. Since top and bottom plates are nailed into all the vertical wall members, they serve to tie the entire wall together.

Corner Posts

Corner posts are constructed wherever a wall ties into another wall. Outside comers are at the ends of a wall. Inside corners occur where a partition ties into a wall at some point between the ends of the wall.

Three typical designs for corner assemblies are shown in figure 1-34. View A shows outside corner construction using only three studs. View B shows outside corner construction using two studs with short blocks between them at the center and ends. A third full-length stud can be used instead of blocks. View C shows inside corner construction using a block laid flat. A full-length stud can be used instead of a block. Note that all corner assemblies should be constructed from straight stud material and should be well nailed. When framing corners, you can use full-length studs or short blocks.

fig0834.jpg (57881 bytes)

Figure 1-34.—Corner posts.

Rough Door and Window Openings

A rough opening must be framed into a wall wherever a door or window is planned. The dimensions of the rough opening must allow for the final frame and for the required clearance around the frame.

Figure 1-35 shows details of rough openings for doors and windows in wood-frame construction. The rough opening for atypical door is framed with a header, trimmer studs, and, in some cases, top cripple studs. The rough opening for a typical window includes the same members as for a dear, plus a rough window sill and bottom cripples.

fig0835.jpg (42593 bytes)

Figure 1-35.—Rough frame openings for doors and windows.

A header is placed at the top of a rough opening. It must be strong enough to carry the weight bearing down on that section of the wall. The header is supported by trimmer studs fitting between the soleplate and the bottom of the header. The trimmer studs are nailed into the regular studs at each side of the header. Nails are also driven through the regular studs into the ends of the header.

The header maybe either solid or built up of two 2 by 4 pieces with a 1/2-inch spacer. The spacer is needed to bring the width of the header to 3 1/2 inches. This is the actual width of a nominal 2 by 4 stud wall. A built-up header is as strong as or stronger than a solid piece.

The type and size of header is shown in the blueprints. Header size is determined by the width of the opening and by how much weight is bearing down from the floor above.

The tops of all door and window openings in all walls are usually in line with each other. Therefore, all headers are usually the same height from the floor. The standard height of walls in most wind-framed buildings is either 8 feet 3/4 inch or 8 feet 1 inch from the subfloor to the ceiling joists. The standard height of the doors is 6 feet 8 inches.

Cripple studs are nailed between the header and the double top plate of a door opening. These help carry the weight from the top plate to the header. The cripple studs are generally spaced 16 inches OC.

A rough window sill is added to the bottom of a rough window opening. The sill provides support for the finished window and frame to be placed in the wall. The distance between the sill and the header is determined by the dimensions of the window, the window frame, and the necessary clearances at the top and bottom of the frame. Cripple studs, spaced 16 inches OC, are nailed between the sill and soleplate. Additional cripple studs may be placed under each end of the sill.

Bracing

Diagonal bracing is necessary for the lateral strength of a wall. In all exterior walls and main interior partitions, bracing should be placed at both ends (where possible) and at 25-foot intervals. An exception to this requirement is an outside wall covered with structural sheathing nailed according to building specifications. This type of wall does not require bracing.

Diagonal bracing is most effective when installed at a 45 to 60 angle. You can do this after the wall has been squared and still lying on the subfloor. The most widely used bracing system is the 1 by 4 let-in type, as shown in figure 1-36. The studs are notched so that the 1 by 4 piece is flush with the surface of the studs.

Cut-in bracing (fig. 1-36) is another type of diagonal bracing. It usually consists of 2 by 4s cut at an angle and toenailed between studs at a diagonal from the top of a corner post down to the soleplate.

fig0836.jpg (75838 bytes)

Figure 1-36.—Types of bracing.

Diagonal sheathing (fg. 1-36) is the strongest type of diagonal bracing. Each board acts as a brace for the wall. When plywood or other panel sheathing is used, other methods of bracing maybe omitted.

Fire Stops

Most local building codes require fire stops (also known as fire blocks) in walls over 8 foot 1 inch high. Fire stops slow down fire travel inside walls. They can be nailed between the studs before or after the wall is raised. Fire stops can be nailed in a straight line or staggered for easier nailing. Figure 1-37 shows a section of a framed wall with fire stops.

fig0837.jpg (59683 bytes)

Figure 1-37.—Fire blocking.

It is not necessary to nail fire stops at the midpoint of the wall. They can be positioned to provide additional backing for nailing the edges of drywall or plywood.

CONSTRUCTION

All major components of a wall should be cut before assembly. By reading the blueprints, you can determine the number of pieces and lengths of all components. The different parts of the wall are then assembled. Any hard, level surface can be used for assembly. After completing nailing, raise the walls in place for securing.

Two layout procedures are used in wall layout: horizontal plate and vertical layout. In horizontal plate layout, the location of the wall is determined from the dimensions found in the floor plan of the blueprints. For vertical layout, the dimension can be found in the sectional views of the building’s blueprints.

Horizontal Plate Layout

After all the lines are snapped, the wall plates are cut and tacked next to the lines (fig. 1-38). The plates are then marked off for corner posts and regular studs, as well as for the studs, trimmers, and cripples for the rough openings. All framing members must be clearly marked on the plates. This allows for efficient and error-free framing. Figure 1-37 shows a wall with framing members nailed in place according to layout markings.

fig0838.jpg (45532 bytes)

Figure 1-38.—Layout and cutting of plates.

A procedure for marking outside and inside comers for stud-and-block corner post construction is shown in figure 1-39. For laying out studs for the first exterior wall, see figure 1-40. In figure 1-40, the plates are marked for the first stud from a corner to be placed 15 1/4 inches from the end of the turner. Studs after the first stud follow 16 inches OC layout. This ensures the edges of standard-size panels used for sheathing or wallboard fall on the centers of the studs. Cripples are laid out to follow the layout of the studs.

fig0839.jpg (63049 bytes)

Figure 1-39.—Marking inside and outside corners.

fig0840.jpg (37485 bytes)

Figure 1-40.—First exterior wall stud layout.

A procedure for laying out studs for the second exterior wall is shown in figure 1-41. The plates are  marked for the first stud to be placed 15 1/4 inches from the outside edge of the panel thickness on the first wall. This layout allows the corner of the first panel on the second wall to lineup with the edge of the first panel on the second wall. Also, the opposite edge of the panel on the second wall will break on the center of a stud.

fig0841.jpg (35154 bytes)

Figure 1-41.—Second exterior wall stud layout.

A procedure for laying out studs for interior walls (partitions) is shown in figure 1-42. If panels are placed on the exterior wall first, the wall plates for the interior wall are marked for the first stud to be placed 15 1/4 inches from the edge of the panel thickness on the exterior wall. If panels are to be placed on the interior wall, the wall plates of the interior wall are marked for the first stud to be placed 15 1/4 inches from the unpaneled exterior wall.

fig0842.jpg (47368 bytes)

Figure 1-42.—Starting measurement for interior wall.

If drywall or other interior finish panels are to be nailed to an adjoining wall (fig. 1-42, view A), you must measure 15 1/4 inches plus the thickness of the material. When panels are to be nailed on a wall first (view B), measure and mark the 15 1/4 inches from the front surface of the bottom plate. These procedures ensure stud alignment remains accurate throughout the nailing process.

Rough openings for doors and windows must also be marked on the wall plates. The rough opening dimensions for a window (fig, 1-43, view A) or wood door (view B) are calculated based on the window or door width, the thickness of the finish frame, and 1/2-inch clearance for shim materials at the sides of the frame. Some blueprint door and window schedules give the rough opening dimensions, simplifying the layout.

fig0843.jpg (76708 bytes)

Figure 1-43.—Measurements for windows and doors.

A rough opening for a metal window often requires a 1/2-inch clearance around the entire frame. When the measurements are not given in the window schedule, take them from the manufacturer’s installation instructions supplied with the windows.

A completely laid out bottom plate includes markings for corner posts, rough openings, studs, and cripples. The corner posts are laid out first. Next, the 16-inch marks for the studs and cripples are marked, and then the marks for the rough openings are made.

Some Builders prefer to layout the rough openings before the studs and cripples are marked. There is, however, an advantage to laying out the 16-inch OC marks first. Studs and trimmers framing a door and window often fall very close to a 16-inch OC stud mark Slightly shifting the position of the rough opening may eliminate an unnecessary stud from the wall frame.

Vertical Layout

Vertical layout is the procedure for calculating the lengths of the different vertical members of a wood-framed wall. This makes it possible to precut all studs, trimmers, and cripples required for a building.

Some blueprints contain section views giving the exact rough heights of walls. The rough height is the distance from the subfloor to the bottom of the ceiling oists. The rough height to the top of the door (the distance from the subfloor to the bottom of the door header) may also be noted on the section drawing. In addition, it may be given in the column for rough opening measurements on the door schedule. The rough height to the top of the door establishes the measurement for the rough height to the top of the window, as window headers are usually in line with door headers.

The distance from the bottom to the top of a rough window opening can be found by measuring down from the bottom of the window header using dimensions provided in the rough opening column of the window schedule.

Many Builders prefer to frame the door and window openings before assembling the wall. View A of figure 1-44 shows typical door framing; view B shows typical window framing. After stud layout, cripple studs are laid out (usually 16 inches OC) and nailed between the header and top plate and rough window sill and soleplate. It is a good practice to place a cripple stud under each end of a sill.

fig0844.jpg (63579 bytes)

Figure 1-44.—Framing typical door and window openings.

ASSEMBLY

After the corners and openings for doors and windows have been made up, the entire wall can be nailed together .on the subfloor (fig. 1-45). Place top and bottom plates at a distance slightly greater than the length of the studs. Position the corners and openings between the plates according to the plate layout. Place studs in position with the crown side up. Nail the plates into the studs, cripples, and trimmers. On long walls, the breaks in the plates should occur over a stud or cripple.

fig0845.jpg (67935 bytes)

Figure 1-45.—Assembly of wall components.

Placing the Double Top Plate

The double top plate (fig. 1-46) can be placed while the wall is still on the subfloor or after all the walls have been raised. The topmost plates are nailed so that they overlap the plates below at all corners. This helps to tie the walls together. All ends are fastened with two 16d nails. Between the ends, 16d nails are staggered 16 inches OC. The butt joints between the topmost plates should be at least 4 feet from any butt joint between the plates below them.

fig0846.jpg (45565 bytes)

Figure 1-46.—Double top plate.

Squaring Walls and Placing Braces

A completely framed wall is often squared while it is still lying on the subfloor. In this way, bracing, plywood, or other exterior wall covering can be nailed before the wall is raised. When diagonal measurements are equal, the wall is square. Figure 1-47 shows examples of unsquared and squared walls.

fig0847.jpg (23362 bytes)

Figure 1-47.—Squaring a wall.

A let-in diagonal brace maybe placed while the wall is still on the subfloor. Lay out and snap a line on the studs to show the location of the brace (fig. 1-48). The studs are then notched for the brace. Tack the brace to the studs while the wall is still lying on the subfloor. Tacking instead of nailing allows for some adjustment after the wall is raised. After any necessary adjustment is made, the nails can be securely driven in.

fig0848.jpg (18085 bytes)

Figure 1-48.—Let-in diagional brace.

Raising

Most walls can be raised by hand if enough help is available. It is advisable to have one person for every 10 feet of wall for the lifting operation.

The order in which walls are framed and raised may vary from job to job. Generally, the longer exterior walls are raised first. The shorter exterior walls are then raised, and the comers are nailed together. The order of framing interior partitions depends on the floor layout.

After a wall has been raised, its bottom plates must be nailed securely to the floor. Where the wall rests on a wood subfloor and joists, 16d nails should be driven through the bottom plate and into the floor joists below the wall.

Plumbing and Aligning

Accurate plumbing of the comers is possible only after all the walls are up. Most framing materials are not perfectly straight; walls should never be plumbed by applying a hand level directly to an end stud. Always use a straightedge along with the level, as shown in figure 1-49, view A. The straightedge can be a piece ripped out of plywood or a straight piece of 2 by 4 lumber. Blocks 3/4 inch thick are nailed to each end. The blocks make it possible to accurately plumb the wall from the bottom plate to the top plate.

fig0849.jpg (143289 bytes)

Figure 1-49.—Plumbing and aligning corners and walls.

Plumbing corners requires two persons working together-one working the bottom area of the brace and the other watching the level. The bottom end of the brace is renailed when the level shows a plumb wall.

The tops of the walls (fig. 1-49, view B) are straightened (aligned or lined up) after all the corners have been plumbed. Prior to nailing the floor or ceiling joists to the tops of the walls, make sure the walls are aligned. Here’s how: Fasten a string from the top plate atone corner of the wall to the top plate at another corner of the wall. You then cut three small blocks from 1 by 2 lumber, Place one block under each end of the string so that the line is clear of the wall.

The third block is used as a gauge to check the wall at 6- or 8-foot intervals. At each checkpoint, a temporary brace is fastened to a wall stud.

When fastening the temporary brace to the wall stud, adjust the wall so that the string is barely touching the gauge block. Nail the other end of the brace to a short 2 by 4 block fastened to the subfloor. These temporary braces are not removed until the framing and sheathing for the entire building have been completed.

Framing Over Concrete Slabs

Often, the ground floor of a wood-framed building is a concrete slab. In this case, the bottom plates of the walls must be either bolted to the slab or nailed to the slab with a powder-actuated driver. If bolts are used, they must be accurately set into the slab at the time of the concrete pour. Holes for the bolts are laid out and drilled in the bottom plate when the wall is framed. When the wall is raised, it is slipped over the bolts and secured with washers and nuts.

Occasionally, on small projects, the soleplate is bolted or fastened down first. The top plate is nailed to the studs, and the wall is lifted into position. The bottom ends of the studs are toenailed into the plate. The rest of the framing procedure is the same as for walls nailed on top of a subfloor.

SHEATHING THE WALLS

Wall sheathing is the material used for the exterior covering of the outside walls. In the past, nominal 1-inch-thick boards were nailed to the wall horizontally or at a 45 angle for sheathing. Today, plywood and other types of panel products (waferboard, oriented strandboard, compositeboard) are usually used for sheathing. Plywood and nonveneered panels can be applied much quicker than boards. They add considerable strength to a building and often eliminate the need for diagonal bracing.

Generally, wall sheathing does not include the finished surface of a wall, Siding, shingles, stucco, or brick veneer are placed over the sheathing to finish the wall. Exterior finish materials are discussed later in this course.

Plywood

Plywood is the most widely used sheathing material. Plywood panels usually applied to exterior walls range in size from 4 by 8 feet to 4 by 12 feet with thicknesses from 5/16 inch to 3/4 inch. The panels may be placed with the grain running vertically or horizontally (fig. 1-50). Specifications may require blocking along the long edges of horizontally placed panels.

fig0850.jpg (91723 bytes)

Figure 1-50.-Plywood sheathing.

Typical nailing specifications require 6d nails with panels 1/2 inch or less in thickness and 8d nails for panels more than 1/2 inch thick. The nails should be spaced 6 inches apart along the edges of the panels and 12 inches apart at the intermediate studs.

When nailing the panels, leave a 1/8-inch gap between the horizontal edges of the panels and a 1/16-inch gap between the vertical edges. These gaps allow for expansion caused by moisture and prevent panels from buckling.

In larger wood-framed buildings, plywood is often nailed to some of the main interior partitions. The result is called a shear wall and adds considerable strength to the entire building.

Plywood sheathing can be applied when the squared wall is still lying on the subfloor. However, problems can occur after the wall is raised if the floor is not perfectly straight and level. For this reason, some Builders prefer to place the plywood after the entire building has been framed.

Nonveneered Panels

Although plywood is the most commonly used material for wall sheathing, specs sometimes call for nonveneered (reconstituted wood) panels. Panels made of waferboard, oriented strandboard, and composite-board have been approved by most local building codes for use as wall sheathing. Like plywood, these panels resist racking, so no comer bracing is necessary in normal construction. However, where maximum shear strength is required, conventional veneered plywood panels are still recommended.

The application of nonveneered wall sheathing is similar to that for plywood. Nailing schedules usually call for 6d common nails spaced 6 inches OC above the panel edges, and 12 inches OC when nailed into the intermediate studs. Nonveneered panels are usually applied with the long edge of the panel in a vertical position.

METAL FRAMING

Metal is an alternative to wood framing. Many buildings are framed entirely of metal, whereas some buildings are framed in a combination of metal and wood.

The metal framing members generally used are cold-formed steel, electrogalvanized to resist corrosion. Thicknesses range from 18 gauge to 25 gauge, the latter being most common. Most metal studs have notches at each end and knockouts located about 24 inches OC (fig. 1-51) to facilitate pipe and conduit installation. the size of the knockout, not the size of the stud, determines the maximum size of pipe or other material that can be passed through horizontally.

fig0851.jpg (34153 bytes)

Figure 1-51.—Typical metal stud construction.

Chase (or double stud) walls (fig. 1-52) are often used when large pipes, ducts, or other items must pass vertically or horizontally in the walls. Studs are generally available in thicknesses of 1 5/8, 2 1/2, 3 5/8, 4, and 6 inches. The metal runners used are also 25-gauge (or specified gauge) steel or aluminum, sized to complement the studs. Both products have features advantageous to light-frame construction. The metal studs and runners do not shrink swell, twist, or warp. Termites cannot affect them, nor are they susceptible to dry rot. Also, when combined with proper covering material, they have a high fire-resistance rating.

fig0852.jpg (45315 bytes)

Figure 1-52.—Chase wall construction.

A variety of systems have been developed by manufacturers to meet various requirements of attachment, sound control, and fire resistance. Many of the systems are designed for ease in erection, yet they are still remountable for revising room arrangements.

The framing members are assembled with power screwdrivers and using self-drilling, self-tapping screws. The floor assembly is fastened to the foundation or concrete slab with studs (special nails) driven through the stud track (runner) by a powder-actuated stud driver. The plywood subfloor is installed over the metal floor framing system with self-drilling, self-tapping screws and structural adhesive. Wall sections are assembled at the jobsite or delivered as preassembled panels from an off-site prefabrication shop. Conventional sheathing is attached to the framework with self-tapping screws.

Door frames for both the interior partitions and exterior walls are integral with the system. They are preprinted and may come complete with necessary

(fig. 1-53). Friction-tight insulation is installed by placing the batts (bundles of insulating material) between the studs on the exterior walls. Studs are spaced 12, 16, or 24 inches OC as specified in the blueprints.

fig0853.jpg (37031 bytes)

Figure 1-53.—Wood blocking for celling or wall-mounted fixtures.

Corner and Casing Beads

Standard wallboard corner bead is manufactured from galvanized steel with perforated flanges, as shown in figure 1-54. It provides a protective reinforcement of straight corners. The corner bead is made with l-inch by 1-inch flanges for 3/8- or 1/2-jnch single-layer wallboard; 1 inch by 1 1/4 inches for 1/2-inch or 5/8-inch single-layer wallboard; 1 1/4 inches by 1 1/4 inches for two-layer wallboard application. It is available in 10-foot lengths.

fig0854.jpg (10380 bytes)

Figure 1-54.—Standard corner bead.

fig0855.jpg (9755 bytes)

Figure 1-55.—Multiflex tape bead.

Multiflex tape bead consists of two continuous metal strips on the undersurface of 2 1/8-inch-wide reinforcing tape (fig. 1-55). This protects corners formed at any angle. Multiflex tape bead comes in 100-foot rolls.

Casing and trim beads (examples are shown in fig. 1-56) are used as edge protection and trim around window and door openings and as moldings at ceiling angles. They are made from galvanized steel in three styles to fit 3/8-inch, 1/2-inch, and 5/8-inch wallboard and come in 10-foot lengths.

fig0856.jpg (16896 bytes)

Figure 1-56.—Casing and trim beads.

Expansion Joints

Expansion joints are vinyl extrusions used as control joints in drywall partitions and ceilings. A typical form is shown in figure 1-57.

fig0857.jpg (4493 bytes)

Figure 1-57.—Expansion joint.

Figure 1-58 shows a typical metal frame layout and use of corner and casing beads for corners, partition intersections, and partition ends. It also shows a typical cross section of a metal frame stud wall control joint. Figure 1-59 lists the different types of fasteners used in metal frame construction and explains the application of each type.

fig0858.jpg (76549 bytes)

Figure 1-58.—Metal frame layout with various beads and joints.

 

fig0859.jpg (280745 bytes)

Figure 1-59.—Drywall screws and fastening application.

CEILING FRAMING

LEARNING OBJECTIVE:

Upon completing this section, you should be able to state the purpose of ceiling frame members and describe layout and installation procedures.

Ceiling construction begins after all walls have been plumbed, aligned, and secured. One type of ceiling supports an attic area beneath a sloping (pitched) roof. Another type serves as the framework of a flat roof. When a building has two or more floors, the ceiling of a lower story is the floor of the story above.

One of the main structural functions of a ceiling frame is to tie together the outside walls of the building. When located under a pitched roof, the ceiling frame also resists the outward pressure placed on the walls by the roof rafters (fig. 1-60). The tops of interior partitions are fastened to the ceiling frame. In addition to supporting the attic area beneath the roof, the ceiling frame supports the weight of the finish ceiling materials, such as gypsum board or lath and plaster.

fig0860.jpg (32649 bytes)

Figure 1-60.—Ceiling frame tying exterior walls together.

JOISTS

Joists are the most important framing members of the ceiling. Their size, spacing, and direction of travel are given on the floor plan. As mentioned earlier, the spacing between ceiling joists is usually 16 inches OC, although 24-inch spacing is also used. The size of a ceiling joist is determined by the weight it carries and the span it covers from wall to wall. Refer to the blueprints and specifications for size and OC spacing. Although it is more convenient to have all the joists running in the same direction, plans sometimes call for different sets of joists running at right angles to each other.

Interior Support

One end of a ceiling joist rests on an outside wall. The other end often overlaps an interior bearing partition or girder. The overlap should be at least 4 inches. Ceiling joists are sometimes butted over the partition or girder. In this case, the joists must be cleated with a 3/4-inch-thick plywood board, 24 inches long, or an 18-gauge metal strap, 18 inches long.

Ceiling joists may also butt against the girder, supported by joist hangers in the same manner as floor joists.

Roof Rafters

Whenever possible, the ceiling joists should run in the same direction as the roof rafters. Nailing the outside end of each ceiling joist to the heel of the rafter as well as to the wall plates (fig. 1-61) strengthens the tie between the outside walls of the building.

fig0861.jpg (25747 bytes)

Figure 1-61.—Nailing of ceiling joists.

A building may be designed so that the ceiling joists do not run parallel to the roof rafters. The rafters are therefore pushing out on walls not tied together by ceiling joists. In this case, 2 by 4 pieces are added to run in the same direction as the rafters, as shown in figure 1-62. The 2 by 4s should be nailed to the top of each ceiling joist with two 16d nails. The 2 by 4 pieces should be spaced no more than 4 feet apart, and the ends secured to the heels of the rafters or to blocking over the outside walls.

fig0862.jpg (104328 bytes)

Figure 1-62.—2 by 4 ties.

Roof Slope

When ceiling joists run in the same direction as the roof rafters, the outside ends must be cut to the slope of the roof. Ceiling frames are sometimes constructed with stub joists (fig. 1-63). Stub joists are necessary when, in certain sections of the roof, rafters and ceiling joists do not run in the same direction. For example, a low-pitched hip roof requires stub joists in the hip section of the roof.

fig0863.jpg (61742 bytes)
Figure 1-63.—Stub joists.

Ribbands and Strongbacks

Ceiling joists not supporting a floor above require no header joists or blocking. Without the additional header joists, however, ceiling joists may twist or bow at the centers of their span. To help prevent this, nail a 1 by 4 piece called a ribband at the center of the spans (fig. 1-64). The ribband is laid flat and fastened to the top of each joist with two 8d nails. The end of each ribband is secured to the outside walls of the building.

fig0864.jpg (70400 bytes)

Figure 1-64.—Ribband installation.

A more effective method of preventing twisting or bowing of the ceiling joists is to use a strongback. A strongback is made of 2 by 6 or 2 by 8 material nailed to the side of a 2 by 4 piece. The 2 by 4 piece is fastened with two 16d nails to the top of each ceiling joist, as shown in figure 1-65. The strongbacks are blocked up and supported over the outside walls and interior partitions. Each strongback holds a ceiling joist in line and also helps support the joist at the center of its span.

fig0865.jpg (64767 bytes)

Figure 1-65.—Strongback.

 

Layout

Ceiling joists should be placed directly above the studs when the spacing between the joists is the same as between the studs. This arrangement makes it easier to install pipes, flues, or ducts running up the wall and through the roof. However, for buildings with walls having double top plates, most building codes do not require ceiling joists to line up with the studs below.

If the joists are being placed directly above the studs, they follow the same layout as the studs below (fig. 1-66, view A). If the joist layout is different from that of the studs below (for example, if joists are laid out 24 inches OC over a 16 inch OC stud layout), mark the first joist at 23 1/4 inches and then at every 24 inches OC (fig. 1-66, view B).

fig0866.jpg (26105 bytes)

Figure 1-66.—Ceiling joist spacing.

It is a good practice to mark the positions of the roof rafters at the time the ceiling joists are being laid out. If the spacing between the ceiling joists is the same as between the roof railers, there will be a rafter next to every joist. Often, the joists are laid out 16 inches OC and the roof rafters 24 inches OC. Therefore, every other rafter can be placed next to a ceiling joist.

FRAME

All the joists for the ceiling frame should be cut to length before they are placed on top of the walls. On structures with pitched-roofs, the outside ends of the joists should also be trimmed for the roof slope. This angle must be cut on the crown (top) side of the joist. The prepared joists can then be handed up to the Builders working on top of the walls. The joists are spread in a flat position along the walls, close to where the y will be nailed. Figure 1-67 shows one procedure for constructing the ceiling frame. In this example, the joists lap over an interior partition. Refer to the figure as you study the following steps:

  1. Measure and mark for the ceiling joists.
  2. Install the ceiling joists on one side of the building.
  3. Install the ceiling joists on the opposite side of the building.
  4. Place backing on walls running parallel to the joists.
  5. Install 2 by 4 blocks flat between joists where needed to fasten the tops of inside walls running parallel to the joists.
  6. Cut and frame the attic scuttle.
  7. Place strongbacks at the center of the spans.

fig0867.jpg (108253 bytes)

Figure 1-67.—Constructing a typical ceiling frame.

Fastening Walls

The tops of walls running in the same direction as the ceiling joists must be securely fastened to the ceiling frame. The method most often used is shown in figure 1-68. Blocks, 2 inches by 4 inches, spaced 32 inches OC, are laid flat over the top of the partition. The ends of each block are fastened to the joists with two 16d nails. Two 16d nails are also driven through each block into the top of the wall.

fig0868.jpg (51269 bytes)

Figure 1-68.—Backing for nailing joists to ceiling frame.

Applying Backing

Walls running in the same direction as the ceiling joists require backing. Figure 1-68 (insert) shows how backing is nailed to the top plates to provide a nailing surface for the edges of the finish ceiling material. Lumber used for backing usually has 2-inch nominal thickness, although l-inch boards are sometimes used.

Figure 1-68 shows backing placed on top of walls. The 2 by 4 pieces nailed to the exterior wall projects from one side of the wall. The interior wall requires a 2 by 6 or 2 by 8 piece extending from both sides of the wall. Backing is fastened to the top plates with 16d nails spaced 16 inches OC. Backing is also used where joists run at right angles to the partition (fig. 1-69).

fig0869.jpg (74663 bytes)

Figure 1-69.—Backing for interior wall plates.

Attic Scuttle

The scuttle is an opening framed in the ceiling to provide an entrance into the attic area. The size of the opening is decided by specification requirements and should be indicated in the blueprints. It must be large enough for a person to climb through easily.

The scuttle is framed in the same way as a floor opening. If the opening is no more than 3 feet square, it is not necessary to double the joists and headers. Scuttles must be placed away from the lower areas of a sloping roof. The opening may be covered by a piece of plywood resting on stops. The scuttle opening can be cut out after all the regular ceiling joists have been nailed in place.

 

David L. Heiserman, Editor

Copyright   SweetHaven Publishing Services
All Rights Reserved

Revised: December 03, 2014